Pto. abierto simplificado de tramitación anticipada, obras denominadas Recuperación de zona verde, adaptación y eliminación de barreras arquitectónicas frente a la catedral, parcela comprendida entre c/ Miguel Hernández, Antonio Gaudí y Gustavo Torner (proyecto remodelación parque Antonio Gaudí), plan de actuación integrado revitaliza mejorada (plan edil), financiación FEDER 21-27
Trabajos de movimiento de tierras · Works concession · Madrid · Lasts 4 months
Should I bid?
To bid you need…
- Submit your bid on the contracting body's platform before 14/12/2026.
- Prove the solvency the notice asks for (further down, under “What they ask for”).
- A technical proposal: the value judgement is 5 % of the points.
What an experienced bidder checks before preparing a bid, with the data behind each point. The decision is yours.
- In favour: 18 days left: there is time for the technical proposal.
- 95 % of the points are decided by figures (the price is worth 70 out of 100); 5 %, by the technical proposal.
- In 17 contracts of this body in the same sector, usually 11 bids are submitted and the winner lowers the price by 25,1 % when there are three bids or more.
- If you win, you have 10 working days to hand in the documents that prove what you declared (art. 150.2 LCSP) and to lodge a performance guarantee of 5 % (up to 18.764 €).
Award criteria
- Mejora 3 · 2,5 points · by formula
- Aumento de plazo de garantía · 5,0 points · by formula
- Propuesta económica. · 70,0 points · by formula
- Mejora 5 · 2,5 points · by formula
- Mejora 2 · 2,5 points · by formula
- Mejora 4 · 2,5 points · by formula
- Mejora 1 · 10,0 points · by formula
- Memoria descriptiva · 5,0 points · value judgement
Solvency required
- ARTÍCULO 88.1.a). Relación de las obras ejecutadas en el curso de los cinco últimos años de igual o similar naturaleza que las que constituyen el objeto del contrato, en la que se indique el importe, la fecha y el destinatario, público o privado, de las mismas. El licitador deberá acreditar que e
- Los empresarios podrán basarse en la solvencia y medios externos de otras entidades, independientemente de la naturaleza jurídica de los vínculos que tengan con ellas, siempre que demuestren que, para la ejecución del contrato, disponen efectivamente de esos medios y la entidad a la que recurra no e
- ARTÍCULO 87.1.a) Volumen anual de negocios, o bien volumen anual de negocios en el ámbito al que se refiera el contrato, referido al mejor ejercicio dentro de los tres últimos disponibles en función de las fechas de constitución o de inicio de actividades del empresario y de presentación de las ofer
- Capacidad de obrar
The notice only lists the means; the amounts are in the specifications.
Short of solvency? Look for a partner for a joint venture (UTE)
In a joint venture (UTE) the solvency of each company is added together. We show you who has won contracts of the same kind for the amount that is missing.
Ask the specifications
An AI assistant is answering you. Only from what the specifications say, citing document and page; each citation is checked. Your question is processed outside your device and we do not store it under your name. What governs is the specifications.
EjemploMade-up data so you can see the result. It doesn't belong to any company or person.
Administrative specifications (PCAP) Read
Saved: Administrative specifications (PCAP), 38 pages.
Once the specifications are read, the questions, the compliance matrix and the proposal work from their text.
Sign in with your email: we'll send you a link, no password
We only keep your email to give you access. Privacy
Prepare my bid
The steps, in the order you do them. You submit on the contracting body's platform, not here.
- Decide whether to bid Should I bid?
- Read what they ask for Ask the specifications · Compliance matrix
- Prepare the paperwork Fill in the annexes of the specifications
- Write the technical proposal Guided technical proposal · Simulated evaluator
- Review your bid Review my bid
- Submit it Submit on each platform · Add the deadline to my calendar
How much winners bid below
En 17 contratos de este órgano en el mismo sector (obras), quien ganó bajó una mediana del 20,1 % (half of them between 9,4 % and 30,3 %). With three or more bids, 25,1 %. Only one bid was submitted in 6 % of them. Work out the abnormally low bid threshold.
How many points your reduction scores
We read the price formula in the specifications and apply it to your reduction against the best of the others.
Documents and notices
What Ayuntamiento de Mejorada del Campo buys and who it awards to · More tenders in Madrid · More tenders: works
Guarantees, payments, appeals and all the data in the notice
Guarantees
Final guarantee: 5 % of the price you bid, excluding VAT. If you bid the base budget, 18.764,03 €; with your reduction, less. It is provided by the bidder with the best offer, before the award.
How it is provided
- Bank guarantee from a bank, savings bank, credit cooperative, financial credit institution or mutual guarantee society: joint and several, waiving the benefit of discussion, payable on first demand and with no end date.
- Surety bond with an insurer authorised in that line.
- Cash or Public Debt securities, at the Caja General de Depósitos (state deposit office) or at the deposit office of the contracting region or local entity.
- Withholding from the price, only if the specifications provide for it.
The final guarantee, as a bank guarantee or surety bond, is deposited at the Caja General de Depósitos or the equivalent deposit office of the contracting administration; the provisional one, as a bank guarantee or surety bond, is handed to the contracting authority.
Check who is vouching for you
Before paying the fee, check that the entity is registered: Bank of Spain register of entities (banks and mutual guarantee societies) or register of insurers of the Directorate-General for Insurance (surety bonds).
Public Sector Contracts Act, articles 106 to 111 (BOE); General Regulation, articles 55 to 59 (BOE); Regulation of the Caja General de Depósitos, article 12 (BOE). Consulted on 7-11-2026. What the specifications of this tender say prevails.
How long it takes to pay
Mejorada del Campo Town Council paid its suppliers in 92,0 days on average (julio–septiembre de 2026). That is above the 30 days the law sets: expect to be paid later, and factor the late-payment interest into your bid.
Source of the data: Ministerio de Hacienda, average supplier payment period (RD 635/2014), consulted on 26-11-2026. When you have to be paid and what to do if you are not.
Won it? Find subcontractors
If you win, part of the work can be subcontracted: local companies with similar work and, if the specifications reserve the contract, special employment centres and integration companies. See subcontractors
Your deadlines in working days
Counted using the calendar of the authority's seat: Mejorada del Campo (Comunidad de Madrid) (Law 39/2015, art. 30).
- If they ask you for the documents (art. 150.2)
- If the request reaches you today, 26/11/2026: 10 working days from the day after Thursday 26 November 2026. Expires on Monday 14 December 2026.
If the act was published the same day on the contracting authority's profile, the deadline counts from the sending of the notification, not from when you open it (LCSP, Additional Provision 15): always use the earliest date.
Skipped, besides weekends:
- 07/12/2026 · Lunes siguiente a Día de la Constitución Española regional holiday, Comunidad de Madrid
- 08/12/2026 · Immaculate Conception national holiday
Excluding Saturdays, Sundays and national public holidays. Public holidays of Comunidad de Madrid are also deducted. Local holidays of Mejorada del Campo are deducted. Any day that the Administration's calendar of non-working days adds (art. 30.6 and 30.7 of Law 39/2015) also extends the period.
Datos de festivos.io — CC BY 4.0 — https://festivos.io. Códigos postales: GeoNames — CC BY 4.0 — https://www.geonames.org.Count another deadline with your calendar (API: since, dias, cp_organo, cp_interesado).
If you are excluded or disagree
This contract is below 3.000.000 € of estimated value: it is not subject to the special appeal. Its acts are appealed under Law 39/2015 and Law 29/1998 on the contentious-administrative jurisdiction (art. 44.6). Before submitting, review your bid so that there is nothing to appeal. Source: LCSP, art. 44: recurso especial en materia de contratación, actos recurribles (consolidated text, accessed on 7 November 2026).
| Contracting authority | Junta de Gobierno del Ayuntamiento de Mejorada del Campo |
|---|---|
| Case reference | 14274/2026 |
| Type of contract | Works concession |
| Procedure | Open |
| Régimen | Ley de Contratos del Sector Público |
| Base budget excluding VAT | 375.280,54 € |
| Base budget including VAT | 454.089,45 € |
| Estimated value | 375.280,54 € |
| Place of performance | Madrid |
| CPV | 45112500 · Trabajos de movimiento de tierras; 45316100 · Instalación de equipo de alumbrado exterior; 45432100 · Trabajos de pavimentación y revestimiento de suelos; 45112710 · Trabajos de paisajismo en zonas verdes |
| End of the submission period | 14/12/2026 at 23:59 (18 days left) |
| Status | Open for bids |
| Final guarantee | 5,0 % |
Régimen de esta licitación
- Ley de Contratos del Sector Público Ley 9/2017, de Contratos del Sector Público (LCSP)
Contrato regido por la Ley 9/2017. - Fondos de la UE Código de financiación EU
La financiación europea trae obligaciones de información y de publicidad: el pliego las detalla. - Fondo Europeo de Desarrollo Regional (FEDER) Código de financiación FEDER
La financiación europea trae obligaciones de información y de publicidad: el pliego las detalla.
Origen de los datos: Ministerio de Hacienda (Plataforma de Contratación del Sector Público). Actualizado el 24/11/2026 a las 13:35. No somos una plataforma de contratación: la oferta se presenta en la del órgano.