Obra de rehabilitación de edificio municipal en Calle Segovia de La Línea (Cádiz)
Trabajos de construcción de locales comerciales, almacenes y edificios industriales, edificios relacionados con el transporte · Works contract · Cádiz · Lasts 12 months
Should I bid?
To bid you need…
- Submit your bid on the contracting body's platform before 15/12/2026.
- Prove the solvency the notice asks for (further down, under “What they ask for”).
- A technical proposal: the value judgement is 30 % of the points.
What an experienced bidder checks before preparing a bid, with the data behind each point. The decision is yours.
- In favour: 19 days left: there is time for the technical proposal.
- 70 % of the points are decided by figures (the price is worth 40 out of 100); 30 %, by the technical proposal.
- In 38 contracts of this body in the same sector, usually 2,5 bids are submitted and the winner lowers the price by 8,6 % when there are three bids or more.
- In favour: In 32 % of them there was only one bid: competition is usually low.
- If you win, you have 7 working days to hand in the documents that prove what you declared (art. 159.4 LCSP) and to lodge a performance guarantee of 5 % (up to 61.961 €).
- Simplified open procedure: no provisional guarantee, and you must be registered in ROLECE (art. 159.4.a LCSP).
Award criteria
- Análisis del proyecto · 10,0 points · value judgement
- experiencia personal técnico adscrito al contrato · 15,0 points · by formula
- Incremento del plazo de garantía de la obra · 5,0 points · by formula
- Memoria constructiva y programa de trabajos · 15,0 points · value judgement
- Implantación norma UNE-EN ISO 9001 para actividades relacionadas con la ejecución de obras de edificación · 7,0 points · by formula
- criterio económico mediante fórmula · 40,0 points · by formula
- Implantación norma UNE-EN ISO 14001 para actividades relacionadas con la ejecución de obras de edificación · 3,0 points · by formula
- Presentación de Plan de Control de Calidad · 5,0 points · value judgement
Solvency required
- Compromiso adscripción medios epígrafe 14 CCC. Los licitadores presentan Declaración responsable, según modelo anexo. Solo el ganador deberá acreditar, documentalmente según epigrafe 18 CCC, disponer de dichos medios
- Capacidad de obrar
- Estar prerregistrado en el ROLECE, y declarar que no ha habido modificaciones en los datos registrados
The notice only lists the means; the amounts are in the specifications.
Short of solvency? Look for a partner for a joint venture (UTE)
In a joint venture (UTE) the solvency of each company is added together. We show you who has won contracts of the same kind for the amount that is missing.
Ask the specifications
An AI assistant is answering you. Only from what the specifications say, citing document and page; each citation is checked. Your question is processed outside your device and we do not store it under your name. What governs is the specifications.
EjemploMade-up data so you can see the result. It doesn't belong to any company or person.
Administrative specifications (PCAP) Read
Saved: Administrative specifications (PCAP), 38 pages.
Once the specifications are read, the questions, the compliance matrix and the proposal work from their text.
Sign in with your email: we'll send you a link, no password
We only keep your email to give you access. Privacy
Prepare my bid
The steps, in the order you do them. You submit on the contracting body's platform, not here.
- Decide whether to bid Should I bid?
- Read what they ask for Ask the specifications · Compliance matrix
- Prepare the paperwork Fill in the annexes of the specifications
- Write the technical proposal Guided technical proposal · Simulated evaluator
- Review your bid Review my bid
- Submit it Submit on each platform · Add the deadline to my calendar
How much winners bid below
En 38 contratos de este órgano en el mismo sector (obras), quien ganó bajó una mediana del 6,6 % (half of them between 1,2 % and 12,1 %). With three or more bids, 8,6 %. Only one bid was submitted in 32 % of them. Work out the abnormally low bid threshold.
How many points your reduction scores
We read the price formula in the specifications and apply it to your reduction against the best of the others.
Published by the authority
- aprobacion proyecto
- Acuerdo de iniciación del expediente
- REPLANTEO
- Documento de aprobación del expediente
- Memoria justificativa
Documents and notices
What Ayuntamiento de la Línea de la Concepción buys and who it awards to · More tenders in Cádiz · More tenders: works
Guarantees, payments, appeals and all the data in the notice
Guarantees
Final guarantee: 5 % of the price you bid, excluding VAT. If you bid the base budget, 61.960,57 €; with your reduction, less. It is provided by the bidder with the best offer, before the award.
How it is provided
- Bank guarantee from a bank, savings bank, credit cooperative, financial credit institution or mutual guarantee society: joint and several, waiving the benefit of discussion, payable on first demand and with no end date.
- Surety bond with an insurer authorised in that line.
- Cash or Public Debt securities, at the Caja General de Depósitos (state deposit office) or at the deposit office of the contracting region or local entity.
- Withholding from the price, only if the specifications provide for it.
The final guarantee, as a bank guarantee or surety bond, is deposited at the Caja General de Depósitos or the equivalent deposit office of the contracting administration; the provisional one, as a bank guarantee or surety bond, is handed to the contracting authority.
Check who is vouching for you
Before paying the fee, check that the entity is registered: Bank of Spain register of entities (banks and mutual guarantee societies) or register of insurers of the Directorate-General for Insurance (surety bonds).
Public Sector Contracts Act, articles 106 to 111 (BOE); General Regulation, articles 55 to 59 (BOE); Regulation of the Caja General de Depósitos, article 12 (BOE). Consulted on 7-11-2026. What the specifications of this tender say prevails.
How long it takes to pay
La Línea de la Concepción Town Council paid its suppliers in 13,5 days on average (julio–septiembre de 2026). Within the 30 days the law sets.
Source of the data: Ministerio de Hacienda, average supplier payment period (RD 635/2014), consulted on 26-11-2026. When you have to be paid and what to do if you are not.
Won it? Find subcontractors
If you win, part of the work can be subcontracted: local companies with similar work and, if the specifications reserve the contract, special employment centres and integration companies. See subcontractors
Your deadlines in working days
Counted using the calendar of the authority's seat: Línea de la Concepción, La (Andalucía) (Law 39/2015, art. 30).
- If they ask you for the documents (art. 150.2)
- If the request reaches you today, 26/11/2026: 7 working days from the day after Thursday 26 November 2026. Expires on Wednesday 9 December 2026.
If the act was published the same day on the contracting authority's profile, the deadline counts from the sending of the notification, not from when you open it (LCSP, Additional Provision 15): always use the earliest date.
Skipped, besides weekends:
- 07/12/2026 · Lunes siguiente a Día de la Constitución Española regional holiday, Andalucía
- 08/12/2026 · Immaculate Conception national holiday
Excluding Saturdays, Sundays and national public holidays. Public holidays of Andalucía are also deducted. Local holidays of Línea de la Concepción, La are deducted. Any day that the Administration's calendar of non-working days adds (art. 30.6 and 30.7 of Law 39/2015) also extends the period.
Datos de festivos.io — CC BY 4.0 — https://festivos.io. Códigos postales: GeoNames — CC BY 4.0 — https://www.geonames.org.Count another deadline with your calendar (API: since, dias, cp_organo, cp_interesado).
If you are excluded or disagree
This contract is below 3.000.000 € of estimated value: it is not subject to the special appeal. Its acts are appealed under Law 39/2015 and Law 29/1998 on the contentious-administrative jurisdiction (art. 44.6). Before submitting, review your bid so that there is nothing to appeal. Source: LCSP, art. 44: recurso especial en materia de contratación, actos recurribles (consolidated text, accessed on 7 November 2026).
| Contracting authority | Alcaldía del Ayuntamiento de la Línea de la Concepción |
|---|---|
| Case reference | 130/26 |
| Type of contract | Works |
| Procedure | Simplified open |
| Régimen | Ley de Contratos del Sector Público |
| Base budget excluding VAT | 1.239.211,32 € |
| Base budget including VAT | 1.499.445,70 € |
| Estimated value | 1.239.211,32 € |
| Place of performance | Cádiz |
| CPV | 45213000 · Trabajos de construcción de locales comerciales, almacenes y edificios industriales, edificios relacionados con el transporte; 45000000 · Trabajos de construcción; 45200000 · Trabajos generales de construcción de inmuebles y obras de ingeniería civil; 45211000 · Trabajos de construcción de inmuebles de viviendas colectivas y unifamiliares; 45210000 · Trabajos de construcción de inmuebles |
| End of the submission period | 15/12/2026 at 14:00 (19 days left) |
| Status | Open for bids |
| Final guarantee | 5,0 % |
Régimen de esta licitación
- Ley de Contratos del Sector Público Ley 9/2017, de Contratos del Sector Público (LCSP)
Contrato regido por la Ley 9/2017.
Origen de los datos: Ministerio de Hacienda (Plataforma de Contratación del Sector Público). Actualizado el 25/11/2026 a las 14:00. No somos una plataforma de contratación: la oferta se presenta en la del órgano.