Contrato de obras para la ejecución del proyecto de rehabilitación/reforma integral de viviendas para destinarlas a personas sin hogar en los barrios de Santa Adela, Beiro y el Fargue del municipio de Granada, en el marco del Plan de Recuperación, Transformación y Resiliencia - Financiado por la Unión Europea - Next Generation EU
Trabajos de construcción · Works contract · Granada · Lasts 6 months
Should I bid?
To bid you need…
- Submit your bid on the contracting body's platform before 10/12/2026.
- Prove the solvency the notice asks for (further down, under “What they ask for”).
- The ESPD (your statement that you meet the requirements): the contracting body publishes its own and you can prepare it here.
- A technical proposal: the value judgement is 40 % of the points.
What an experienced bidder checks before preparing a bid, with the data behind each point. The decision is yours.
- In favour: 16 days left: there is time for the technical proposal.
- 60 % of the points are decided by figures (the price is worth 40 out of 100); 40 %, by the technical proposal.
- In 62 contracts of this body in the same sector, usually 2 bids are submitted and the winner lowers the price by 12,3 % when there are three bids or more.
- In favour: In 35 % of them there was only one bid: competition is usually low.
- If you win, you have 10 working days to hand in the documents that prove what you declared (art. 150.2 LCSP) and to lodge a performance guarantee of 5 % (up to 17.587 €).
Award criteria
- Experiencia del equipo de trabajo en actuaciones similares · 20,0 points · by formula
- Memoria Constructiva · 40,0 points · value judgement
- Oferta económica · 40,0 points · by formula
Solvency required
- Anexo VI Compromiso de adscripción de medios para la ejecución del contrato
- Anexo V Declaración responsable del cumplimiento de los requerimientos legales en materia social y laboral
- Anexo VII DEUC
The notice only lists the means; the amounts are in the specifications.
Short of solvency? Look for a partner for a joint venture (UTE)
In a joint venture (UTE) the solvency of each company is added together. We show you who has won contracts of the same kind for the amount that is missing.
Ask the specifications
An AI assistant is answering you. Only from what the specifications say, citing document and page; each citation is checked. Your question is processed outside your device and we do not store it under your name. What governs is the specifications.
EjemploMade-up data so you can see the result. It doesn't belong to any company or person.
Administrative specifications (PCAP) Read
Saved: Administrative specifications (PCAP), 38 pages.
Once the specifications are read, the questions, the compliance matrix and the proposal work from their text.
Sign in with your email: we'll send you a link, no password
We only keep your email to give you access. Privacy
Prepare my bid
The steps, in the order you do them. You submit on the contracting body's platform, not here.
- Decide whether to bid Should I bid?
- Read what they ask for Ask the specifications · Compliance matrix
- Prepare the paperwork Fill in the ESPD · Fill in the annexes of the specifications
- Write the technical proposal Guided technical proposal · Simulated evaluator
- Review your bid Review my bid
- Submit it Submit on each platform · Add the deadline to my calendar
How much winners bid below
En 62 contratos de este órgano en el mismo sector (obras), quien ganó bajó una mediana del 8,2 % (half of them between 1,0 % and 13,0 %). With three or more bids, 12,3 %. Only one bid was submitted in 35 % of them. Work out the abnormally low bid threshold.
How many points your reduction scores
We read the price formula in the specifications and apply it to your reduction against the best of the others.
Published by the authority
Documents and notices
What Ayuntamiento de Granada buys and who it awards to · More tenders in Granada · More tenders: works
Guarantees, payments, appeals and all the data in the notice
Guarantees
Final guarantee: 5 % of the price you bid, excluding VAT. If you bid the base budget, 17.587,42 €; with your reduction, less. It is provided by the bidder with the best offer, before the award.
How it is provided
- Bank guarantee from a bank, savings bank, credit cooperative, financial credit institution or mutual guarantee society: joint and several, waiving the benefit of discussion, payable on first demand and with no end date.
- Surety bond with an insurer authorised in that line.
- Cash or Public Debt securities, at the Caja General de Depósitos (state deposit office) or at the deposit office of the contracting region or local entity.
- Withholding from the price, only if the specifications provide for it.
The final guarantee, as a bank guarantee or surety bond, is deposited at the Caja General de Depósitos or the equivalent deposit office of the contracting administration; the provisional one, as a bank guarantee or surety bond, is handed to the contracting authority.
Check who is vouching for you
Before paying the fee, check that the entity is registered: Bank of Spain register of entities (banks and mutual guarantee societies) or register of insurers of the Directorate-General for Insurance (surety bonds).
Public Sector Contracts Act, articles 106 to 111 (BOE); General Regulation, articles 55 to 59 (BOE); Regulation of the Caja General de Depósitos, article 12 (BOE). Consulted on 7-11-2026. What the specifications of this tender say prevails.
How long it takes to pay
Granada Town Council paid its suppliers in 19,5 days on average (abril–junio de 2026). Within the 30 days the law sets.
Source of the data: Ministerio de Hacienda, average supplier payment period (RD 635/2014), consulted on 19-11-2026. When you have to be paid and what to do if you are not.
Won it? Find subcontractors
If you win, part of the work can be subcontracted: local companies with similar work and, if the specifications reserve the contract, special employment centres and integration companies. See subcontractors
Your deadlines in working days
Counted using the calendar of the authority's seat: Andalucía (Law 39/2015, art. 30).
- If they ask you for the documents (art. 150.2)
- If the request reaches you today, 24/11/2026: 10 working days from the day after Tuesday 24 November 2026. Expires on Thursday 10 December 2026.
If the act was published the same day on the contracting authority's profile, the deadline counts from the sending of the notification, not from when you open it (LCSP, Additional Provision 15): always use the earliest date.
Skipped, besides weekends:
- 07/12/2026 · Lunes siguiente a Día de la Constitución Española regional holiday, Andalucía
- 08/12/2026 · Immaculate Conception national holiday
Excluding Saturdays, Sundays and national public holidays. Public holidays of Andalucía are also deducted. To deduct local holidays too, enter the postcode of the authority's seat; meanwhile, each local holiday that falls within the period extends it by one day. Any day that the Administration's calendar of non-working days adds (art. 30.6 and 30.7 of Law 39/2015) also extends the period.
Count another deadline with your calendar (API: since, dias, cp_organo, cp_interesado).
If you are excluded or disagree
This contract is below 3.000.000 € of estimated value: it is not subject to the special appeal. Its acts are appealed under Law 39/2015 and Law 29/1998 on the contentious-administrative jurisdiction (art. 44.6). Before submitting, review your bid so that there is nothing to appeal. Source: LCSP, art. 44: recurso especial en materia de contratación, actos recurribles (consolidated text, accessed on 7 November 2026).
| Contracting authority | Junta de Gobierno del Ayuntamiento de Granada |
|---|---|
| Case reference | OBR-2026000102 |
| Type of contract | Works |
| Procedure | Open |
| Régimen | Ley de Contratos del Sector Público |
| Base budget excluding VAT | 351.748,31 € |
| Base budget including VAT | 425.615,46 € |
| Estimated value | 351.748,31 € |
| Place of performance | Granada |
| CPV | 45000000 · Trabajos de construcción; 45400000 · Acabado de edificios; 45300000 · Trabajos de instalación en edificios |
| End of the submission period | 10/12/2026 at 17:30 (16 days left) |
| Status | Open for bids |
| Final guarantee | 5,0 % |
Régimen de esta licitación
- Ley de Contratos del Sector Público Ley 9/2017, de Contratos del Sector Público (LCSP)
Contrato regido por la Ley 9/2017. - Fondos de la UE Código de financiación EU
La financiación europea trae obligaciones de información y de publicidad: el pliego las detalla. - Plan de Recuperación, Transformación y Resiliencia (PRTR) Código de financiación PRTR
Aplican las obligaciones del PRTR: mira la lista de abajo.
Antes de presentar, con el PRTR
- •Declaración de ausencia de conflicto de intereses (DACI) Orden HFP/1030/2021, anexo IV.A
Es obligatoria para quienes participan en los procedimientos de ejecución del PRTR; su modelo es el del anexo IV.A. Mira en el pliego si te piden la tuya y quién la firma. - •Titular real de tu empresa Orden HFP/55/2023, art. 7
El órgano analiza el riesgo de conflicto de interés con la información de titularidad real de la AEAT; si la AEAT no la tiene de tu empresa, el órgano puede pedirte esa información. Ten a mano nombre, apellidos, fecha de nacimiento y participación de cada titular real. - •NIF, razón social y domicilio fiscal de tu empresa y de las subcontratistas Orden HFP/1030/2021, art. 8
El pliego debe pedírtelos para cumplir las obligaciones de información del PRTR. - •Aceptación de la cesión de datos entre administraciones Orden HFP/1030/2021, anexo IV.B
Declaración con el modelo del anexo IV.B. - •Compromiso de cumplimiento de los principios transversales del PRTR Orden HFP/1030/2021, anexo IV.C
Declaración responsable con el modelo del anexo IV.C. - •Alta en el censo de empresarios de la AEAT con la actividad que de verdad ejerces Orden HFP/1030/2021, art. 8
Hay que acreditar la inscripción en el Censo de empresarios, profesionales y retenedores (o el censo foral equivalente), que debe reflejar la actividad desarrollada cuando participas.