El objeto de la presente contratación, mediante Acuerdo Marco, es la prestación de servicios de transporte para atender las necesidades de movilidad derivadas del programa AVT2200 2ºBatch durante la estancia en España del alumnado y personal asociado..
Servicios especiales de transporte de pasajeros por carretera · Services contract · España · Lasts 21 months
Award criteria
- Según PCP y PPT · 100,0 points · by formula
Solvency required
- Según PCP y PPT
- No estar incurso en incompatibilidades
- No prohibición para contratar
- Cumplimiento con las obligaciones tributarias
- Capacidad de obrar
- Para las empresas extranjeras, declaración de sometimiento a la legislación española.
- Cumplimiento con las obligaciones con la Seguridad Social
The notice only lists the means; the amounts are in the specifications.
Ask the specifications
An AI assistant is answering you. Only from what the specifications say, citing document and page; each citation is checked. Your question is processed outside your device and we do not store it under your name. What governs is the specifications.
EjemploMade-up data so you can see the result. It doesn't belong to any company or person.
Administrative specifications (PCAP) Read
Saved: Administrative specifications (PCAP), 38 pages.
Once the specifications are read, the questions, the compliance matrix and the proposal work from their text.
Sign in with your email: we'll send you a link, no password
We only keep your email to give you access. Privacy
How much winners bid below
En 19 contratos de este órgano en el mismo sector (transporte), quien ganó bajó una mediana del 0,0 % (half of them between 0,0 % and 0,6 %). Only one bid was submitted in 79 % of them. Work out the abnormally low bid threshold.
Documents and notices
What Navantia S.A., S.M.E. buys and who it awards to · More tenders: transport
Guarantees, payments, appeals and all the data in the notice
Won it? Find subcontractors
If you win, part of the work can be subcontracted: local companies with similar work and, if the specifications reserve the contract, special employment centres and integration companies. See subcontractors
Minimum staff cost under the collective agreement
In services, staff cost sets the minimum price you can bid. Choose the collective agreement, enter its pay scale and check whether your bid covers it (art. 149.4 LCSP). Work out the staff cost
Your deadlines in working days
Counted using the calendar of the authority's seat: Madrid (Comunidad de Madrid) (Law 39/2015, art. 30).
- Recurrir el anuncio o los pliegos
- Notice published on 02/11/2026: 15 working days from the day after Monday 2 November 2026. Expires on Tuesday 24 November 2026.
Si recurres los pliegos, hazlo antes de presentar tu oferta (art. 50.1.b).
Skipped, besides weekends:
- 09/11/2026 · Nuestra Señora de la Almudena local holiday, Madrid · source: Comunidad de Madrid — Festivos locales (datos abiertos)
- If they ask you for the documents (art. 150.2)
- If the request reaches you today, 23/11/2026: 10 working days from the day after Monday 23 November 2026. Expires on Wednesday 9 December 2026.
If the act was published the same day on the contracting authority's profile, the deadline counts from the sending of the notification, not from when you open it (LCSP, Additional Provision 15): always use the earliest date.
Skipped, besides weekends:
- 07/12/2026 · Lunes siguiente a Día de la Constitución Española regional holiday, Comunidad de Madrid
- 08/12/2026 · Immaculate Conception national holiday
Excluding Saturdays, Sundays and national public holidays. Public holidays of Comunidad de Madrid are also deducted. Local holidays of Madrid are deducted. Any day that the Administration's calendar of non-working days adds (art. 30.6 and 30.7 of Law 39/2015) also extends the period.
Datos de festivos.io — CC BY 4.0 — https://festivos.io. Códigos postales: GeoNames — CC BY 4.0 — https://www.geonames.org.Count another deadline with your calendar (API: since, dias, cp_organo, cp_interesado).
If you are excluded or disagree
If something in the notice or the specifications prevents you from bidding, or if the committee leaves out your bid, you can go for free before a specialised tribunal: the special appeal on procurement, which is voluntary (art. 44.7).
- What you can appeal
- The tender notice, the specifications and the contract documents.
- Procedural acts that decide on the award, prevent continuing or leave a party defenceless; in any case, the admission or rejection of candidates and bidders and the admission or exclusion of bids, including those excluded as abnormally low (art. 149).
- The award decision.
- Certain contract modifications (arts. 204 and 205), assignments to in-house bodies and concession buy-backs.
- Before which tribunal
- It depends on the administration the contracting authority belongs to: the TACRC if it is a State one (art. 45) and the region's tribunal if it is regional or local (art. 46). See the table of tribunals. Source: LCSP, art. 46: órgano competente en las comunidades autónomas y entidades locales (consolidated text, accessed on 7 November 2026).
- Deadline
- 15 working days (art. 50.1). They are counted from the day after: the publication of the notice, for the notice and for the specifications (if the notice says how to access them); the day you learned of the act, for procedural acts such as an exclusion; the notification of the award. If you want to appeal the specifications, do so before submitting your bid (art. 50.1.b). The period keeps running while you ask to see the file (art. 52.2). Appealing the award suspends the procedure (art. 53). The appeal can be filed at the contracting authority's registry or at the tribunal's (art. 51.3).Source: LCSP, art. 50: iniciación del procedimiento y plazo (consolidated text, accessed on 7 November 2026).
- Applicable case law
- What is appealed and how long it takes. In 2025 the TACRC received 2.226 appeals (in 2024, 1.824). The award was appealed in 43,58 % of cases, the specifications in 25,18 % and the exclusion in 19,99 %. 15,85 % of appeals were upheld in full and 6,59 % in part; 46,95 % were dismissed and 30,64 % ended without a ruling on the merits. The average time to decide was 55 calendar days (in 2024, 46), counted from when the Tribunal has the file. Source: Memoria 2025 del Tribunal Administrativo Central de Recursos Contractuales (financial year 2025, pp. 14 and 17).
- OIReScon. The 2025 annual supervision report asks for attention to exclusions for bids deemed abnormal and to formal grounds for exclusion. Source: Informe anual de supervisión 2025 de la OIReScon: conclusiones y recomendaciones (approved on 22 December 2025). Source: Buscador de informes consultivos (OIReScon) (accessed on 7 November 2026).
- Junta Consultiva de Contratación Pública del Estado. Before leaving you out for a defect in the documents of the request (art. 150.2), they must give you a chance to correct it if it is not an absolute breach and the requirement already existed when the deadline expired. Source: Junta Consultiva de Contratación Pública del Estado, expediente 6/2021 (art. 150.2 LCSP) (file 6/2021). Source: Informes de la Junta Consultiva de Contratación Pública del Estado (accessed on 7 November 2026).
- Rulings and judgments. Search the TACRC decisions, case law on the CENDOJ. Where to look for those of your region's tribunal.
Everything about the special appeal · Review your bid before submitting it · Answer a formal request
| Contracting authority | Comité Central de Compras de Navantia S.A., S.M.E. |
|---|---|
| Case reference | 5100077108 AM Servicio de transporte |
| Type of contract | Services |
| Procedure | Open |
| Régimen | Ley de Contratos del Sector Público |
| Estimated value | 750.000,00 € |
| Place of performance | España |
| CPV | 60130000 · Servicios especiales de transporte de pasajeros por carretera; 60100000 · Servicios de transporte por carretera |
| End of the submission period | 23/11/2026 at 14:00 (period closed) |
| Status | Deadline closed; award pending |
Régimen de esta licitación
- Ley de Contratos del Sector Público Ley 9/2017, de Contratos del Sector Público (LCSP)
Contrato regido por la Ley 9/2017.
Origen de los datos: Ministerio de Hacienda (Plataforma de Contratación del Sector Público). Actualizado el 02/11/2026 a las 13:19. No somos una plataforma de contratación: la oferta se presenta en la del órgano.